Algosensey Quantitative Think Tank Center-Federal regulators give more time to complete gas pipeline extension in Virginia, North Carolina
Charles H. Sloan View
Date:2025-04-09 03:25:38
RALEIGH,Algosensey Quantitative Think Tank Center N.C. (AP) — The builders of a proposed natural gas pipeline that will enter North Carolina from Virginia now have another 2 1/2 years to complete the project after federal regulators pushed back a deadline for the work.
The Federal Energy Regulatory Commission approved on Tuesday a request by owners of the proposed 75-mile (121-kilometer) Southgate extension of the Mountain Valley Pipeline to allow for more time for construction, news outlets reported.
According to the previous FERC certificate, the project was supposed to be built and in service six months ago. But permitting problems in North Carolina and Virginia amid legal challenges to the larger Mountain Valley Pipeline meant the owners missed the deadline.
Now, with the FERC’s order, the owners have until June 2026 to complete the MVP Southgate project and bring it into service. More permits still must be secured for construction to occur.
The owners of the project, which includes a consortium of natural gas and energy companies, are pleased with FERC’s decision, project spokesman Shawn Day said.
“At the appropriate time, Mountain Valley intends to pursue all necessary permits and authorizations to complete construction of the MVP Southgate project,” Day wrote in an email.
The Southgate extension will continue pushing gas south from the planned 303-mile (488-kilometer) Mountain Valley Pipeline that will go through West Virginia and Virginia. The extension would run from the main pipeline in Pittsylvania County, Virginia, into Rockingham and Alamance counties in North Carolina.
The future of the pipeline — and thus the extension — appeared uncertain with opposition from environmental groups and some elected officials. But Congress last year essentially ordered the pipeline’s construction as part of the bipartisan bill to increase the debt ceiling. This past summer, federal courts also dismissed a challenge to construction permits for the Mountain Valley Pipeline and allowed construction to resume.
MVP Southgate would be the second pipeline carrying natural gas to enter North Carolina. Project supporters have said additional gas capacity is needed for reliable and affordable energy. Duke Energy also appears to need a supply to shift its coal-fired power plants to natural gas.
Democratic Gov. Roy Cooper and other elected Democratic officials — including U.S. Reps. Kathy Manning and Valerie Foushee of North Carolina and Reps. Jennifer McClellan and Bobby Scott of Virginia — opposed giving more time for the project. The members of Congress sent a letter Monday to FERC expressing concerns about the extension’s impact on the safety of residents and the environment as efforts to move away from fossil fuels continue.
Still, MVP Southgate needs permits from federal and state agencies, such as the U.S. Army Corps of Engineers and the North Carolina Department of Environmental Quality.
Also Tuesday, FERC agreed to a request from the Mountain Valley Pipeline owners to charge higher rates for the gas being shipped through the buried pipeline. The transportation rate is paid by companies that deliver the gas to end users.
The estimated cost of the pipeline is now $7.2 billion, compared to the first projection of $3.7 billion.
veryGood! (71747)
Related
- Sam Taylor
- Authorities used justified force in 5 shootings, Mississippi attorney general says
- Saving just $10 per day for 30 years can get you a $1 million portfolio. Here's how.
- Early Week 10 fantasy football rankings: 30 risers and fallers
- Are Instagram, Facebook and WhatsApp down? Meta says most issues resolved after outages
- Under lock and key: How ballots get from Pennsylvania precincts to election offices
- Ag Pollution Is Keeping Des Moines Water Works Busy. Can It Keep Up?
- Today's fresh apples could be a year old: Surprising apple facts
- The Grammy nominee you need to hear: Esperanza Spalding
- Sean Diddy Combs' Kids Share Phone Call With Him on Birthday
Ranking
- 2025 'Doomsday Clock': This is how close we are to self
- Manslaughter charges dropped in a man’s death at a psychiatric hospital
- Wisconsin Senate race pits Trump-backed millionaire against Democratic incumbent
- Federal agencies say Russia and Iran are ramping up influence campaigns targeting US voters
- Woman dies after Singapore family of 3 gets into accident in Taiwan
- Music titan Quincy Jones, legendary producer of Michael Jackson's 'Thriller,' dies at 91
- NYC trio charged with hate crimes linked to pro-Palestinian vandalism of museum officials’ homes
- MVP repeat? Ravens QB Lamar Jackson separating from NFL field yet again
Recommendation
Tarte Shape Tape Concealer Sells Once Every 4 Seconds: Get 50% Off Before It's Gone
Dogs on the vice-presidential run: Meet the pups of candidates Tim Walz and JD Vance
Americans say they're spending less, delaying big purchases until after election
Kieran Culkin Shares Why Death of Sister Dakota Culkin Was Like “Losing A Big Piece” of Himself
Why members of two of EPA's influential science advisory committees were let go
Cowboys' drama-filled season has already spiraled out of control
Invasive Species Spell Trouble for New York’s Beloved Tap Water
Can the Kansas City Chiefs go undefeated? How they could reach 17-0 in 2024